Guangzhou distributed photovoltaic power generation project management approach (draft for soliciting opinions)

Arctic star solar PV network news: according to Guangzhou administrative normative file management provides, and Guangzhou administrative normative file developed rules, provides, by Guangzhou development and Reform Committee drafted of Guangzhou distributed PV power project management approach (sought views draft) and Guangzhou solar PV power project construction special funds management approach (sought views draft) Yu September 18 up in Guangzhou development and Reform Committee website Shang full text announced. In order to improve the quality of normative documents, so that broad public participation in, and is now open for amendments. Hope that active participation of the public and all segments of society may login to submit comments before the September 28; or send written comments to the Guangzhou Municipal Development and Reform Commission’s Energy Department. Guangzhou Municipal Development and Reform Commission will be based on the careful study of positive efforts to encourage reasonable views and recommendations as required to complete the drafting and approval.

Guangzhou distributed photovoltaic power generation project management policy (draft for soliciting opinions), which read as follows:

Chapter I General provisions

First to actively promote photovoltaic applications, accelerate the construction of distributed solar power projects, to further standardize the photovoltaic power generation project management, forwarding under the Guangdong provincial development and Reform Commission National Energy Board issued the notice on issuance of interim measures for the management of distributed solar power projects (Guangdong development and reform to the new (2014), 37th), spiritual and practical work in this city, this management approach.

Article management approach called “distributed solar power projects”, refers to area industrial parks, enterprises in Guangzhou plant, logistics bases, public buildings as well as residential buildings, such as the roof or side facade construction of solar photovoltaic power projects. Grid integration of distributed PV power generation projects into the power grid planning, for electric power and energy balance, and considering the regulation of grid. Distributed grid-connected PV power generation projects have all Internet access, all for personal use and spontaneous use power more than three, chosen by the project owners.

Article management method of distributed solar power projects involved in managing content mainly include the project file, project, project acceptance, grid-connected electricity metering for water, electricity and access charges, subsidies paid, operation management, and so on.

Chapter II responsibilities

Article development and reform agency responsible for the management of distributed solar power projects. Municipal development and Reform Commission is responsible for co-ordinating management of distributed PV power generation projects in the city, size of project records, all responsible for information collection and management, project development, level, and in conjunction with the City Department of Finance issued finance special funds distributed photovoltaic subsidy program; district development and reform Bureau is responsible for the management of distributed solar power projects in this region, responsibilities for the size of the project file, project information and statistics, submissions, and so on.

Fifth City Department of finance is responsible for city-level grant funds budget management, according to the relevant provisions of the Treasury centralized payment appropriated funds, the municipal development and Reform Commission approved the implementation of a project, issued a funding plan, organize and implement financial inspection and performance assessment.

Article sixth power supply Department is responsible for distributing electricity photovoltaic grid-connected power generation project access, statistics, subsidy payments and other related work. Guangzhou power supply Bureau responsible for distributed grid-connected photovoltaic project access, settlement and subsidies to pay for electricity, collecting and filing of distributed solar power projects for household record, summarize, and submitted to the PV project-related information such as area power supply Bureau responsible for receiving applications for grid-connected, households depending on permissions provide grid access, one-stop management of distributed PV projects PV project-related information services, statistics in the region.

Chapter III administration of scale

Seventh energy Administration Department under the State Council for needed State funding subsidised distributed PV balance of total amount of scale management and annual guidance. Provincial energy departments in accordance with State issued the annual guide scale decomposition and released at the municipal level throughout the annual guide scale. Municipal development and Reform Commission practice of this municipality, the province issued the annual guide scale is decomposed and released in various districts.

Eighth of municipal development and Reform Commission in accordance with the order of distributed solar power projects to be completed and put into operation developed into the city’s annual project plan all guidance, and incorporated into the city’s annual guidance range of dynamic management of project, according to project actual completion time to fine-tune the plan, based upon the facts of city projects, sizing recommendations to the provincial energy departments in a timely manner.

Nineth article in accordance with the provisions of the completion of the relevant procedures and household PV power generation projects and automatically included in the city’s annual guide scale, receive relevant support policy.

Fourth chapter of project construction management

The tenth item record. Need to incorporate the city’s annual guidance range of distributed solar power projects, submitted to the municipal development and Reform Commission for the record. Among them, the household PV power generation projects to the respective district offices of the Department of business directly receive filing related materials, after Guangzhou power supply Bureau Summary by quarter reported to the municipal development and Reform Commission and annual guide scale applied for entry into the city. Do not need to be incorporated into the city’s annual guidance range of distributed solar power projects, but in the above district-level development and reform Department filing.

Article 11th record of distributed solar power projects, the project owner should be implemented effectively in accordance with the filing organization. Really need to change the project owner, address, building size, building ownership and so on, should go through the relevant procedures to the original filing Department, distributed PV power generation projects that must govern the transfer of rights and responsibilities involved. Unauthorized alteration, failure to implement projects without grid access.

12th distributed photovoltaic project for the record you want to fill in the application form for corporate capital investment projects in Guangdong Province, and provide the following materials:

(A) the basic situation of project reporting: includes project name, address, building size, building conditions, engineering technology, business model, implementation plans, economic assessment, etc;

(B) the project construction company business license and organization code certificate (household items to provide personal identity card photocopy);

(C) projects with a total investment over 20% of certificates of deposit to the bank account;

(D) project is based on proof of ownership documents for buildings;

(E) building roof or side elevation of the project contract or agreement (using its own building construction are not required to provide);

(Vi) grid-connected electricity sector agreed that the intention document;

(VII) required to approve bidding plan, submitted tenders basic statistics;

(VIII) other required materials.

13th article other administrative examination and approval procedures. Distributed solar power projects after the filing and other administrative examination and approval procedures can be simplified, eliminating the power business licenses, building permits for the project, environmental impact assessment, energy-saving assessments, soil and water conservation, shock absorption, such as disaster prevention, land use planning and site selection and pre-trial procedures.

Article 14th distributed PV power generation projects involving building, should not affect the safety of its original structure and function, related to the design, construction and operations shall comply with the requirements of the relevant standards.

15th to participate in construction of distributed solar power projects for the design, construction, testing and operating enterprise must have the appropriate qualification.

Article 16th distributed PV projects subject to approval by CNCA certification bodies the certification of photovoltaic products. Product selection should be consistent with safety certification, energy saving, environmental protection and other related provisions of the State.

Article 17th project acceptance. Needs of distributed photovoltaic grid-connected power generation must be issued upon completion of the project to completion. Project owner should be entrusted to a national laboratory accreditation certificate of inspection issued by the institution of distributed PV systems for detection and test reports, inspection includes but is not limited to PV modules, inverters, combiner box, AC and DC power distribution equipment, transformers, safety and power quality detection. Distributed residential photovoltaic power generation project by supplying the Organization for the harmonization of inspection.

Chapter fifth grid access, electricity metering, tariff and subsidy and settlement

Article 18th by the electricity Department is responsible for distributing photovoltaic grid-connected power generation project access, electricity metering, tariff and subsidy matters such as settlement, concrete operational procedures in the light of the China Southern power grid company distributed PV Services Guide (interim) implementation.

The sixth chapter the information management

19th of municipal development and Reform Commission is responsible for co-ordinating the city’s photovoltaic project information management, responsible for summary records, construction and operation of the project information, submitted to the provincial development and Reform Commission on a quarterly basis (new energy industry).

20th district development and reform Bureau carry out regular collection and compilation of distributed solar power projects within their respective jurisdictions for the record, the construction and operation of information, distributed PV project construction in completing this operation information sheets, quarterly submitted to the municipal development and Reform Commission.

Article 21st of the project construction project information management, completing this unit of distributed solar power projects run information tables, quarterly submitted to the municipal development and Reform Commission, and copied to the area in which the project development and reform Bureau.

22nd reported household PV projects in Guangzhou power supply Bureau and the construction of making households distributed PV project construction and operation of an information sheet, submitted to the municipal development and Reform Commission on a quarterly basis.

Article 23rd Guangzhou power supply Bureau responsible for summarizing my municipal, electricity photovoltaic network within the region, and other related information and funds disbursed, fill in grid services and subsidies fund information sheets, quarterly submitted to the municipal development and Reform Commission.

24th all relevant units should strengthen the management of project information, designate a person to serve as information liaisons, timely, accurate, complete and submit the relevant information, and in the first month of every quarter 5 working days before quarterly information report on municipal development and Reform Commission (the Energy Department).

The seventh chapter

25th/2014-2020 years, Guangzhou Municipal-level financial resources earmarked special funds to support the city’s solar photovoltaic power generation application. After grid connected projects, or running for a year, on October 15 of each year, requests for funds or individuals can apply for subsidies to the municipal development and Reform Commission, issued 1 funding plan in principle before the end of November each year. Specific reporting requirements are detailed in the Guangzhou construction of photovoltaic projects of the interim measures for the administration of special funds.

26th annual guide scale target range of distributed solar power projects, within two years from the date of filing was not completed, canceled in its annual guide scale, and cancel the qualification of State subsidies.

27th article in an existing roof or side facade construction of distributed solar power projects, roof or side facade used since the signing of the agreement is not started within six months from the date of the item as well as the failure to submit the required information, and enjoy relevant policies to support qualification shall be cancelled.

The eighth chapter by-laws

28th article of the management practices from the date of promulgation, valid for 5 years. Problems encountered in the implementation process please do not hesitate to reflect to the municipal development and Reform Commission.

Original title: Guangzhou distributed photovoltaic power generation project management approach (draft for soliciting opinions)