Bingtuan development and Reform Commission on issuing the Corps PV interim measures for the management of notifications

Polaris solar PV net news: energy to send a modified FA [bingtuan development and Reform Commission on issuing the Corps 2014]134, PV power plant project notice of interim measures for the Administration

Division development and Reform Commission:

For the implementation of the national energy administration of the PV power plant project management of the interim measures (new [2013]329) documents and normative Corps PV power plant project management, guarantee safe and reliable operation of photovoltaic power plant and power system, promoting the sustained and healthy development of the photovoltaic industry, now of the PV power plant project in bingtuan interim measures for the administration of the issuance of your, please comply.

Bingtuan development and Reform Commission

On February 28, 2014

Corps interim measures for PV power plant project management

Chapter I General provisions

PV power plant project management first to standardize the bingtuan, pursuant to the National Energy Board the PV power plant project management interim measures request, combined with the actual regiments, these measures are formulated.

Second applies as a public power plant construction and operation management of PV power projects.

Bingtuan development and Reform Commission article under the guidance of the State Council Energy Department, responsible for the regiment’s photovoltaic power station of overseeing the construction and operation of the project. Division development and Reform Commission in charge of the Division overseeing the construction and operation of PV projects.

Chapter II administration of planning guidance and scale

Fourth article each Division development reform Board in annually December 5 Qian according to “integrated planning, and reasonable layout, and near access, and local elimination NA” of construction principles, summary this area PV station project built production and the run situation, prepared completed including construction scale, and project layout, and grid access, and power elimination na evaluation and construction plans, content of each Division PV station project construction Xia a annual implementation programme recommends, reported Corps development reform Board.

Fifth article Corps development reform Board according to Corps solar PV power development planning and State Energy competent sector issued to Corps of annual guide sex scale, and each Division PV station project construction and run situation, combines each Division grid access, and power elimination na, and PV station construction conditions,, on each Division development reform Board reported of PV station project construction annual implementation programme recommends for integrated assessment, this based Shang prepared full Corps Xia a annual PV station project construction implementation programme recommends, reported State Energy competent sector.

Sixth Regiment assigned by the written reply of the State Council Energy Department photovoltaic power plant project annual implementation programme is bingtuan development and Reform Commission to record based on the PV. Been incorporated into the energy Administration Department under the State Council approved the construction of the annual implementation plan-scale PV projects and do not enjoy the National Development Fund for renewable energy subsidies.

Article seventh Legion annual construction programme focus has a demonstration effect and significance of high-tech photovoltaic projects; giving priority to construction of photovoltaic projects, master of the works well; settled in priority support corps construction of photovoltaic power generation equipment manufacturing enterprises in bingtuan PV power generation projects. Not need State subsidies and organizations through tendering, competitive construction of photovoltaic power generation project is not subject to annual limits.

Chapter project management

Eighth Division development and Reform Commission is responsible for the project application report the first instance will be short-listed project filed an application to bingtuan development and Reform Commission.

Application reporting project with new energy sources accordingly should consult qualified units, the report includes the following and related accessories:

(A) the basic situation of the project, including copies of business license and copy of the, newly established enterprises without industrial and commercial registration, provided by stakeholders on project cooperation agreement effective documents;

(B) the proposed project;

(C) the project site or a site representative for more than one year in a row the measured data analysis of solar radiation and solar energy resources assessment results;

(D) in accordance with the “access, nearby local absorptive” outcome of the analysis of the principle of the power to dissolve;

(E) the grid access;

(F) the project units provide the authenticity of commitments;

(VII) shall be presented in accordance with the relevant laws and regulations of other files.

Nineth bingtuan development and Reform Commission on the review of compliance with filing conditions project, project registration card issued.

PV power station project is completed after filing of the tenth article, teacher development units to implement reform Commission should guide project planning and site selection, land pre-trial, environmental energy-saving assessment, social impact assessment, risk assessment, financing and other construction conditions, related supporting documents in time to start construction.

11th item registration card is valid for 1 year, counted from date of issue. Items that are not completed within the validity period, no longer applied for the National Development Fund for renewable energy subsidies.

Units shall not be altered without the 12th item PV filing important matters, including project investment, project siting, construction and other major boundary conditions. To alter the main project of boundary conditions, the Corps no longer declared national development and Reform Commission renewable energy development fund subsidies and suspended such enterprises to apply for inclusion in the annual implementation plan.

Construction and operation of the fourth chapter

13th PV design and installation shall comply with the relevant specifications and safety regulations, equipment standards, engineering specifications and other requirements, project design, consultation, installation and supervision of the company shall have corresponding qualifications stipulated by the State.

Article 14th PV solar modules, inverters and other equipment shall comply with national provisions adopted the certification and accreditation body for certification testing.

15th power grid enterprises shall, in accordance with national energy agency PV power plant project on the issuance of the interim measures for the management of notifications (new (2013), No. 329) and photovoltaic power generation project management interim measures requested in Xinjiang Autonomous Region, set up and improve audit and service program of PV power projects pick up nets.

16th section units shall be in accordance with the relevant regulatory requirements of the project, do a grid-connected PV safety, in conjunction with the grid companies active rectification projects security issues in the operation, ensure that PV power stations safe and reliable operation of power systems.

The fifth chapter, industry monitoring and market surveillance

Article 17th projects after completion of the principal part of the project and associated electricity transmission project, the project unit should promptly organize acceptance and will submit the completion report bingtuan development and Reform Commission and CC countries solar power generation technology of centralized management unit. Bingtuan development and Reform Commission, cooperate with the State Council Department in charge of energy, timely organization qualified advisory bodies, through the completion of construction and put into operation more than 1 year after the key project construction and operation of evaluation, the project unit should be run according to the evaluation report on the project facilities and management to carry out the necessary improvements.

Article 18th Division development and Reform Commission is responsible for the Division of PV power station project construction and operation of information and statistics, and runs every month last month the Division project, electricity, electricity, electricity tariffs and subsidies and settlement and other information submitted in bingtuan development and Reform Commission. Meanwhile, in July each year, the following January to form on the semi-annual and annual statistics report, submit the bingtuan development and Reform Commission.

19th Regiment PV projects around the development and Reform Commission will be based on the annual implementation plan completion, construction and operation of the actual situation, as determining the next year an important basis for the Division’s annual construction scale and distribution, have been evident to abandon power and divisions that are not resolved in a timely manner, stop the Division reported annual PV power station project construction implementation plan. Poor implementation of the construction Division, the corresponding reduction next year to implement programmes indicators.

Article 20th during construction, commissioning and operation of PV power projects, such as casualties and major damage and accidents, the project unit should be provided promptly to the Corps safety production supervision departments and Corps energy industry Management Department report if found key equipment quality problems, the project unit should report to bingtuan development and Reform Commission for the first time.

The sixth chapter supplementary articles

Article 21st deadline prior to the issuance of this approach, bingtuan development and Reform Commission has approved the project document is equivalent to the filing, record time in accordance with the approval date.

22nd article this way to be interpreted by the bingtuan development and Reform Commission.

23rd herein from the date of promulgation.