Issued in wushan County, Chongqing City on PV implementation programmes of poverty alleviation project notice

Polaris solar PV net news: Township people’s Governments and neighborhood offices, relevant departments of the County Government, the authorities concerned:

The photovoltaic project implementation programme for poverty alleviation, wushan County has County Government agree that is issued to you, please organize the implementation. Wushan County, poverty alleviation and Development Office

The August 3, 2015

PV project, wushan County implementation plan

In order to further implement the industrial poor “to village, household, persons” requirements, help poor people build sustainable poverty alleviation project to increase, according to the opinions on promoting poverty alleviation work (wushan (2015), 4th) spirit, develop photovoltaic projects for poverty alleviation programmes.

One, overall objectives

Centering function of ecological conservation development, Chongqing, according to the city’s PV industry master plan calls for poverty alleviation, develop photovoltaic industries for poverty alleviation. 2015-2017, the total installed PV power capacity to 6000KW (poor village total installed capacity up to 4020KW), projects with a total investment of 58.8 million Yuan (municipal capital of 13 million Yuan, supporting 15.4 million Yuan at the county level, farmers account for 10.6 million Yuan, the social capital of 19.8 million yuan), guided cards the poor become rich, 6000 people out of poverty.

Second, basic principles

1, overall planning, step by step. Considering the County’s poor households ‘ income needs, power load and power grid construction, unified planning and implement photovoltaic projects, distributed PV and concentrated solar power stations for poverty alleviation to poverty alleviation.

2, policy support, relying on the market. PV-integrated pro-poor policies, policies and related taxes, prices, financial services and network policy, photovoltaic projects for poverty alleviation through the market mechanism.

3, social participation, and work together to advance. Encouraging corporate social responsibility, by way of donations or donations of equipment, active participation in PV poverty action, solve PV equipment and funds, guide social capital to invest in photovoltaic power plant.

4, improve standards, guaranteeing quality. According to various geographical features, economic development and appropriate models for poverty alleviation, improve PV anti-poverty projects quality management system, protect the PV project investment efficiency, strengthening PV poor engineering quality supervision.

Third, the task

1, 2015, the total installed capacity of 930KW, 300 new 3KW distributed photovoltaic power stations, 30KW 1 concentrating photovoltaic power stations. Project investment of 8.1 million Yuan (supporting municipal capital of 2.7 million Yuan, the County of 3 million Yuan, farmers account for 2.4 million yuan), 1200 people out of poverty.

2, 2016, the total installed capacity of 2780KW (poor village 1800KW 980KW social investment). Built in 60 poor village 30KW centralized PV 60. Project investment of 18 million Yuan (municipal capital of 6 million Yuan, the County set 7.2 million Yuan, farmers account for 4.8 million yuan), 3000 people out of poverty. Guide social capital investment of 9.8 million Yuan into agricultural photovoltaic and photovoltaic facilities, achieving 980KW of installed capacity.

3, 2017, the total installed capacity of 2290KW (poor village 1290KW, social investment 1000KW). 43 poor villages built 30KW centralized PV 43, project investment of 12.9 million Yuan (4.3 million Yuan at the city level, county-level matching of 5.2 million Yuan, farmers account for 3.4 million yuan), 1800 people out of poverty. Guide social capital investment of 10 million Yuan into agricultural photovoltaic and photovoltaic facilities, implementation capacity 1000KW.

Four specific steps

1 investigate thoroughly. In village find out of poor villages and poor basic conditions, including poor villages and poor industrial economic, population, illumination, power status, poor roof and barren slopes and the use of land resources, and identified qualified farmers and address. Rural poverty and ecological poverty relocation settlements for the poor as the preferred choice. Lihu PV system information file, to establish the information management system.

2, policy measures. Develop and implement photovoltaic guidelines on poverty reduction, integration of national and local policies for poverty alleviation and PV industry policy, funded through government subsidies, farmers, bank loans, renewable energy funds, network services and other forms of support of PV for poverty alleviation. Encourage social capital into the photovoltaic industry, technical services and discount interest funds support.

3, and technical guidance. Improve policy coordination, technical specifications and training systems, specifically photovoltaic system for poverty alleviation and responsibility, through market competition mechanism to select subjects, and ensure project quality, investment control, step up skills training, establishing a long-term operation and maintenance system to ensure project quality and efficiency.

4, project supervision. By the County Office for poverty alleviation in conjunction with the municipal people’s Government, strengthen supervision of project implementation. Key regulatory projects implementation, incorporation service, subsidy funds settlement and market order, guaranteed PV pro-poor policies are put in place, maintain a fair and just market order.

Five, safeguard measures

1, organization and leadership. Set up County PV leading group for poverty alleviation, appointed by the County Government Office, the Commission, by letter, poverty alleviation, Weather Bureau, electricity companies, townships project implementation units, responsible for organization and implementation of photovoltaic projects. Office was set up at the County Office of poverty alleviation and those responsible for day-to-day operations, the Township is responsible for the implementation of specific projects.

2, technical services. By the County Office of poverty alleviation and supply company, PV equipment manufacturers to establish technical support system, is responsible for the photovoltaic process technical services for poverty alleviation, including planning, development of engineering technical specifications, quality control, project information systems and so on, throughout project implementation and coordination of policies, provide technical services and guidance.

3, work discipline. Strict implementation of pro-poor policies, not fraud, not thick, no workarounds take poverty alleviation projects and funds.

4, strict examination. PV projects into the annual poverty review content, increase the town/Department and village poverty reduction task force on poverty assessment.

Annex: wushan 2015-2017 PV pro-poor poverty task breakdown


Original title: PV implementation programmes of poverty alleviation project, wushan on the issuance of notifications