Hebei issued ordinary photovoltaic plant indicators of project selection criteria

Polaris solar PV net news: recently, the Hebei provincial development and Reform Commission released on issuing the common PV power station project of Hebei province competitive allocation method of notification, notification requirements common PV power station project configured optimally competitive, enterprises participating in the competitive allocation, if submitted materials to deception to cancel its selection qualifications; scalping indicators business, cancel its project development qualification.

Reads as follows:

Cities (containing Dingzhou, xinji City), national development and Reform Commission (Bureau), State grid electric power company in Hebei province and State grid power company in North Hebei province:

For specification PV power project management, optimization resources configuration, do General PV power station project annual construction plans optimization work, according to national development reform Board, and Energy Council on perfect PV power scale management and implemented competition way Configuration project of guide views (sent modified energy (2016) 1163th,) and I province related policy requirements, now will developed of Hebei province General PV power station project competitive configuration approach issued to you, please pursuant to implementation.

Annex: common PV power station project of Hebei province competitive allocation method

Development and Reform Commission of Hebei province

The June 8, 2016 

Hebei province PV competitive allocation method

(For trial implementation)

Chapter I General provisions

First to standardize the photovoltaic power generation project management, optimizing the allocation of resources, doing the normal PV annual construction plan optimization work according to relevant national and provincial policies, the formulation of the approach.

PV is the second ordinary leads in addition to PV technology demonstration bases, PV scale of poverty alleviation and the State not subject to annual limits on other items.

PV third ordinary competitive allocation (hereinafter referred to as competitive allocation) optimally. Optimization work to follow compliance according to law, the principles of openness, fairness and justice.

Chapter II procedures

Fourth, Hebei provincial development and Reform Committee (hereinafter referred to as provincial development and Reform Commission), according to the State’s ordinary annual construction of the PV scale, organize annual construction plan optimization of project work. Related work will be released to society through the provincial development and Reform Commission Web site.

Article fifth district city and County development and reform in accordance with the unified work arrangements, organization of counties (cities and districts) for enterprise reporting projects in the first instance, and after the first instance of the project reported to the provincial development and Reform Commission.

Sixth provincial development and Reform Commission third party agencies to undertake optimized organizations within the industry experts. Selecting the best experts randomly generated from the database. In the selection process, the expert shall not be contacted individually by selection object.

Article seventh review comments issued by the Group of experts in writing. Expert review comments by the Director of the provincial development and Reform Commission Office examination and publication in the portal site.

Eighth provincial development and Reform Commission based on the review comments and publicity issued annual construction plans of the project results.

At all levels of development and reform Department before Nineth and third parties in the selection process, not to collect any fees for any reason.

Chapter three award criteria

Article tenth project candidates should meet the following conditions: incorporated into the construction of photovoltaic power in the region “Thirteen-Five” development planning; enterprise investment ability, no breach of credit; advanced technology demonstration effect, preliminary working conditions; absorptive grid access and market conditions; participation in price competition; a single project in principle not be less than 20 MW capacity.

11th optimization project should follow to facilitate regional economic development, to improve the efficiency of land utilization, is conducive to technological progress and cost reductions, and conducive to the healthy and sustainable development of the photovoltaic industry.

The fourth chapter selection

12th highest rated content in accordance with the Hebei province of the PV power plant project selection criteria (see annex).

The fifth chapter to strengthen supervision

13th annual construction plans of the project should be made in strict accordance with the National Energy Board issued the notice on implementing renewable energy generation project management (new [2015]358) require, in the National Department of energy renewable energy generation project management information management platform.

Article 14th project investors (shareholders and equity ratio) and the main building are not allowed to change. As adjusted due to mergers and acquisitions, in the same Division of labor within the Group and other reasons, the need to change investment or equity ratio should strictly carry out change procedure according to the relevant State provisions. Project owner for any reason is strictly prohibited to resell the annual construction (grid) programme.

Article 15th all departments and units for any reason is not allowed to charge made the annual construction plans of the enterprise.

16th energy regulator to implementation of effective supervision of project construction.

The sixth chapter supplementary articles

Article 17th of this approach will be based on national and provincial policy changes, timely improved.

18th article this way by the Hebei provincial development and Reform Commission is responsible for the interpretation.

19th article this way as of the date of promulgation.

Annex 1

Hebei province PV power plant project selection criteria

First, the enterprise comprehensive capacity assessment (15 points)

1. was praised by the provincial communications (3)

2. enterprise performance evaluation (3)

① grid 150MW per cent in the province and above (3)

② has today network operation in the province, 100MW and more (2)

③ in the province has been grid-50MW and above (1)

3. evaluation of contributions to local economic development (3)

① the strategic cooperation agreement with the province (3)

II strategic cooperation agreement with the host city (2)

③ the strategic cooperation agreement with the County in which the project (1)

4. participation in the construction of photovoltaic projects (3)

5. the roof have been distributed photovoltaic grid-connected power generation project power (2 points)

6. participate in the beautiful countryside construction and outstanding performance (1)

Second, the price (30 points)

Electricity means electricity prices that reduced subsidies.

1. local Internet benchmark price on the basis of prices no more than 0.05 Yuan, down 0.01 Yuan per 2 points (10 points)

2. on the basis of price by 0.05 Yuan, cuts of no more than 0.07 Yuan, down 0.01 Yuan 2.5 points (15 points)

3. local Internet benchmark price on the basis of prices by 0.08 Yuan with 20 points, 0.09 per cent price cut 25 points, 0.10 off 30 points

Third, the project evaluation of construction (25)

1. evaluation of project progress (15 points)

① has invested funds to budget ones 80% (15 points)

② investment funds to budget ones 50% (10 points)

③ investment funds to budget ones 30% (5 points)

2. access to land, land lease agreement lease certificate of expenditure (2)

3. land approval (5)

① Provincial Land Office land pre-trial comments (5)

Second, the first instance of access to municipal land and resources Bureau of land (3)

4. power grid approval (3)

① provincial (municipal) power grid access system for review comments (3)

Second, the provincial (municipal) power grid access system review meeting minutes (2 minutes)

Four, technology review (20)

Evaluation of photovoltaic modules (20 points)

1. up to the State to determine PV industry “leader” advanced technical indicators (10 points)

2. monocrystalline silicon solar module conversion efficiency 17.5%, polycrystalline silicon solar module conversion efficiency 17%, Silicon, Copper-Indium-Gallium-selenium, cadmium Telluride, and other thin film solar module conversion efficiency are 12.5%, 13.5%, 13.5% and 12.5% (13)

3. monocrystalline silicon solar module conversion efficiency 18%, polycrystalline silicon solar module conversion efficiency 17.5%, Silicon, Copper-Indium-Gallium-selenium, cadmium Telluride, and other thin film solar module conversion efficiency are 13%, 14%, 14% and 13% (16)

4. There are major technological breakthroughs, and in the international leading level (20 points)

Five, land utilization model evaluation (10 minutes)

1. Yue Kwong complementary manner (10 points)

2. Lin Guang, agriculture, light complementary way (8)

3. the use of other land utilization way (7)

Six, a negative rating

1. participation in the competitive allocation of business, such as submitted materials trickery to cancel its selection qualifications

2. acts of scalping indicators enterprise, cancelled its project development qualification

Annex 2

Hebei General optimization of PV power rating sheet


Hebei issued ordinary photovoltaic plant indicators of project selection criteria to resell Enterprise will be disqualified

Hebei issued ordinary photovoltaic plant indicators of project selection criteria to resell Enterprise will be disqualified

Hebei issued ordinary photovoltaic plant indicators of project selection criteria to resell Enterprise will be disqualified

Original title: Hebei normal PV project selection criteria introduced scalping indicators of enterprises will be disqualified