Hebei provincial development and Reform Commission on solar thermal power generation

Polaris solar PV net news: Zhangjiakou City development and Reform Commission, State grid power company in Northern Hebei, the company:

According to the National Energy Board on the construction of solar thermal power generation demonstration project notice (new (2016), No. 223) requirements, as do I, the first solar thermal power generation demonstration projects construction work and related matters are hereby notified as follows:

A review, by the National Energy Board organizational experts, the province has more than 4, 214,000 kW total project (refer to table) be included in the first batch of solar thermal power generation demonstration project.

Second, on request, various demonstration projects should be completed by September 30, the record. Zhangjiakou City development and Reform Commission hold organizations related enterprises, before September 26 will record required to submit relevant documents I.

Third, the model project should strictly abide by its commitment to participate in the review of the technical requirements. In the course of project implementation, will authorize hydropower planning Institute organized experts to the project technical course and indicators for monitoring and evaluation.

Four, project development companies to arrange time, pay close attention to construction, in principle, should be completed and put into operation before the end of 2018; after the completion of the project, project development companies should be promptly submitted to me acceptance scheme, by my Committee in conjunction with the relevant authorities to guide project acceptance.

Five, Northern Hebei power network schedule of construction company in conjunction with demonstration projects, supporting network construction work, ensure that the power transmission project and demonstration projects over the production and electricity generated by a full elimination.

Six, the “Thirteen-Five” period, the solar thermal power plant project are incorporated into the national solar thermal power project management, and only included in the list of demonstration projects, the project may benefit from national tariff subsidies.

Contact person: 0311-88600512 Hou Xiaoli Li Feifei


Hebei provincial development and Reform Commission on solar thermal power generation demonstration project construction notice

Original title: national development and Reform Commission of Hebei province on completes the construction of solar thermal power generation demonstration project work notification

Posted in Solar Charger.