Sichuan province PV centralized Internet access project registration Guide

Polaris solar PV net news: first, the scope of

Enterprises, institutions, social groups, such as not using Government funds to invest in Sichuan province construction of photovoltaic (centralized Internet access) power generation project.

Second, the statutory basis

(A) the administrative approval items really necessary to be retained by the State Council administrative licensing decision (June 2004, promulgated by Decree No. 412) Note 1: “given the investment system reform is under way, involving administrative licensing of fixed asset investment projects according to the existing regulations”.

(B) the State Council on reform of the investment system decision ((2004), 20th), part II (a): “for enterprises not using government investment construction projects, are no longer in place and approval system, different situation and the implementation of approved filing system.”

(C) the State Council notice on adjusting and perfecting the capital system of fixed asset investment projects (guofa (2015), 51st).

(D) publish the State list of Government-approved investment projects (2014) notification (guofa (2014), 53rd): “a construction, business investment fixed assets investment projects within the directory shall be submitted in accordance with the provisions of the relevant project approval authority for approval. Enterprises invested outside of the project, the implementation of records management. Public institutions, social groups to invest in the projects, in accordance with the table of contents “.

(E) the Sichuan provincial people’s Government on the release of the list of Government-approved investment projects (in Sichuan province in 2015) notifications (Chuan-fu (2015), 26th): “a, enterprises in Sichuan province-wide directory of investment in fixed assets investment and construction projects, projects shall be submitted with appropriate permission pursuant to the provisions approved by the approval authority. Enterprises invested outside of the project, the implementation of records management. Public institutions, social groups to invest in the projects, in accordance with the table of contents “.

(F) the National Energy Board on issuing < interim measures for pv power plant project management > notice (new (2013), No. 329) 14th: “provincial energy departments based on the Department of State investment project management provides for filing of PV power plant project management. Record project should be consistent with the national solar power development plan and the Energy Department issued annual guide of the area scale indicators and annual implementation plan, has been implementing grid. “

(VII) investment project in Sichuan province for the record of the interim measures (chuan FA (2005), 17th).

Third, the eligibility criteria

(A) comply with relevant national and provincial laws and regulations;

(B) according to the photovoltaic industry policies, industry standards;

(C) meet the capital system of fixed asset investment projects concerning the minimum capital ratio requirements.

Four, application materials


Sichuan province PV (centralized Internet access) project registration Guide

Five, procedure

(A) applicants to the provincial development and Reform Commission provincial Government Affairs Service Center window to submit application materials.

(B) the provincial development and Reform Commission forms review window. On belongs to accepted range, application material complete, and meet statutory form of, spot accepted and issued accepted notice; on application material not complete or not meet statutory form of, in received application material Hou 2 a days within one-time written told applicants need correction of all content; on not belongs to accepted range of, not accepted and issued not accepted notice, and told to has accepted permission of organ application.

(C) record review of the provincial development and Reform Commission. Agree to record project, the provincial development and Reform Commission issued the notification of investment projects for the record; disagreed for the record of the project, issued the notification of corporate investment projects for the record shows no reason for filing, and inform the applicant of the right to apply for administrative reconsideration or bring an administrative lawsuit in accordance with law.

(D) applicants with personal identification (valid ID cards, temporary residence permits, booklet, etc) and technology to provincial Government Affairs Service Center window to receive the result of provincial development and Reform Commission.

Six, processing time

Total processing time: 12 working days.

(A) administrative decision time: 10 working days.

(B) the permit and notify the applicant pick-up time: 2 business days.

Seven, charging basis, standards

Free of charge.

VIII, decision documents

Notice of enterprise investment projects for the record

Nine, of quantitative restrictions

-Free.

Ten, contact

(A) contact number

Sichuan Provincial Government Affairs Service Center province development and reform commissions window: (028) 86917061, 86913671

(B) online-do Hall

Electron Government affair Hall of Sichuan Province: dzzwdt.SC.gov.CN

Sichuan Provincial Government Affairs Service Hall: egov.sczw.gov.CN

Sichuan provincial development and Reform Commission: www.sczw.gov.CN

(C) complaints

Effectiveness of administrative complaints, Sichuan province Tel: 96960

Sichuan Provincial Government Affairs Service Center: (028) 86931019

The Sichuan provincial development and Reform Commission: (028) 86705791

XI notes

(A) has record of project has following situation one of of, project units should timely to written form to original project record organ report and application again record: project investment subject occurred changes of; project total investment occurred changes and is expected to changes range up record investment 20% above of; project construction scale adjustment and is expected to changes range up record construction scale 20% above of; project main construction content and products technology programme occurred changes of; project construction locations occurred changes of.

(B) the project subject to tender according to law, with the tender conditions, the tender submitted for the record by the regulation authorities approved or reported to the relevant authorities for the record.

(C) the project notice of filing is valid for one year, counted from the date of issuance. Within the validity period has not started construction of the project, the project unit should hand in the project record notice expires 30th filing authority to apply for an extension to the original project, the original project filing authority should report to project the decision whether or not to grant an extension before the expiry of the notice. Not start construction within the project in the project record validity does not apply to the project filing authority deferred, the original filing notices expire automatically after the expiry of the validity period of the project, not as a basis for the relevant procedures.

(D) prior to the construction projects have the record, because the list of Government-approved investment projects or changes to build content for the approval of management, according to fixed asset investment projects and approval project proposals for approval.

Original title: 1. the enterprises, institutions, social groups to invest in fixed-asset investment projects licensed 1-2-1. PV (centralized Internet access) project registration Guide