Hubei ordered 2016 general scale indicator total PV power station 1 8 million

Polaris solar PV net news: the shennongjia forestry district, city, State, and city of straight pipe, development and Reform Commission (Department of energy), the relevant County, city and district development and reform Bureau (Department of energy), State power grid of Hubei electric power company:

According to national development reform Board National Energy Council on perfect PV power scale management and implemented competition way Configuration project of guide views (sent modified energy (2016) 1163th,), and national energy Council on issued 2016 years PV power construction implementation programme of notification (country can new can (2016) 166th,), and national energy Council on adjustment 2016 years PV power construction scale about problem of notification (country can new can (2016) No. 383,) requirements, My Bureau, Hubei Province engineering consulting companies, respectively, in September 2016 2016 and December organizations common PV competition selection work. According to the competition than the election result was proposed to be included in the 2016 list PV scale target projects, determined by the Secretary Office and submitted to the National Energy Board approval. 2016 is ordinary PV scale indicator breakdown release, and related matters as follows:

First, with regard to state our province’s 2016 ordinary PV scale indicator

June 2016, the National Energy Board issued 2016 General added scale PV power station 600,000-kilowatt in our province. In December 2016, the National Energy Board issued a reward in our province-building size 200,000-kilowatt, up-scale 1 million-kilowatt. 2016 National Energy Board total issued ordinary index scale PV power station 1.8 million-kilowatt in our province.

Second, on the 1.8 million-kilowatt scale index distribution

According to the National Energy Board notice requirements, as well as energy Secretary Office size will determine the 2016 target assignment principle, 1.8 million-kilowatt size distribution is as follows:

I 600,000-kilowatt the size of the province issued specification 340,000-kilowatt record assigned to the 2016 years ago and before December 30, 2016 completion of eligible projects, the remaining 260,000-kilowatt assigned by September 2016 competition selection sort (see annex). The energy Bureau of Hubei Province notified about 2016 issued ordinary PV scale indicator (e-energy new energy (2016) 122th, hereinafter referred to as e-energy new energy (2016) 122th text) have been assigned to specific projects.

Reward I 200,000-kilowatt scale indicator in the province, 10,000-kilowatt for network investment and construction of Hubei electric power company full solar projects, the remaining 190,000-kilowatt to replace the e-energy new energy (2016) 2017 assigned to 122th scale indicators. (See annex)

Additional 1 million-kilowatt scale indicator in the province, and 30,000-kilowatt for the year 2014 for the record of Huang Yuan huangshitieshan 50MWp photovoltaic power plant into operation in 2016 project, 50,000-kilowatt is used to replace the e-energy new energy (2016) 2017 assigned to 122th scale target, the remaining 920,000-kilowatt assigned by December 2016 competition selection sort. (See annex)

Third, on the project price

Competing assignments and get the scale target projects, within the specified period of time after the completion of (grid to grid-connected power grid Enterprise acceptance, whichever), in accordance with the project promise when we compare the competitive price, by the price Department approval before implementation.

Four, the requirements

(A) projects awarded the 2016 size indicator units in accordance with the commitment of time, pay close attention to promoting the construction of projects. Is a project must be completed by the end of June 2017 grid (grid to grid-connected power grid Enterprise acceptance, whichever), no node is in accordance with the provisions of the project construction, will cancel its assigned size indicators. II was involved in the September of competitive selection of projects must be strictly in accordance with the Declaration in the project implementation plan clear utility model, design, layout, design standards, equipment performance and carry out projects. Not in accordance with the implementation plan calls for the construction of projects, will cancel its assigned size indicators. Third, project units are not allowed to change the investment and equity, building size and construction sites, such as content, production was unauthorized transfers and changes of the project construction, will cancel its assigned size indicators.

(B) development and reform (energy) sector to increase the scale index assigned PV power station construction supervision and coordination services, and urge the units in accordance with the provisions of the project, design standards to promote projects for problems discovered in the inspection to timely inform the provincial energy Bureau. While under the National Energy Board issued the notice on implementing renewable energy generation project management (national new energy (2015), No. 358) requests, information statistics and submit work for photovoltaic power generation project, and through the national renewable energy generation project information management platform for complete information. Municipalities, State development and Reform Commission (Department of energy) photovoltaic power plant for the record in a timely manner after the Summary submitted to the provincial energy Board.

(C) the grid companies to issue in a timely manner the project network and supporting transmission project-building, ensure that project completed timely operation.

(D) under the National Energy Board notice requirements, issued by the National Energy Board will no longer scale index 2017 for new construction in our province. More than of State construction projects in the future, are not allowed into the scope of State renewable energy development fund subsidies. Throughout the development and reform (energy) sector to do investment tips, guide enterprises to work reasonably orderly project. According to “who invests, decision-making, who take risks” principle, indicators of future state the province the size of foreign enterprises ‘ decision to start the construction of the project, cannot be covered by State renewable energy development fund subsidies caused losses borne by the enterprises themselves.

Provincial energy Bureau, jointly with relevant departments, PV power station construction of the size of the allocation targets tracking and timely public photovoltaic power plant in the province-building information, and guide the healthy and orderly development of photovoltaic power plant construction across the province.

The energy Bureau of Hubei Province notified about 2016 issued ordinary PV scale indicator (e-energy new energy (2016) 122th) are inconsistent with this circular, this circular shall prevail.

Energy Bureau of Hubei Province

The January 12, 2017


Hubei ordered 2016 general scale indicator total PV power station 1.8 million-kilowatt

Original title: issued by the Department of energy about the 2016 General PV power plant in Hubei Province scale indicator alerts